The medium combustion plant requirements of the PPC 2018 amendment regulations are designed to control emissions of sulphur dioxide (SO2), nitrogen oxides (NOx) and dust into the air from plants with a net rated thermal input of between 1 and 50 megawatts (MW), contributing to better air quality and reducing the potential risks to human health and the environment.
If you operate your own boiler, engine or generator (including back-up/stand by) for the production of heat or power you may be running a medium combustion plant (MCP), and it is likely you will have to apply for a permit from us or the NIEA if operated on a Part A or Part B installation to continue using it.
This page is designed to help you understand if the legislation is relevant to you and, if it is, what you have to do, when you have to do it by and how we can help you.
The process below will help you decide whether you need to apply. If you already know you need to apply please check the contents of this page to find information to help you do this.
Do I need to register my boiler, generator or engine?
Do you have a boiler, generator or engine burning any fuel which was put into operation before 20 Dec 2018?
Yes – go to step 2.
No – if your plant was put into operation after 20 December 2018 it should already have a Medium Combustion Plant permit. If you do not, contact us at
Does it have a capacity of 5 megawatts (MW) net rated thermal input or more but less than 50MW?
Yes – go to step 3.
The input is higher – you should already have a PPC permit. If not contact the NIEA
The input is lower – if your plant is between 1 and 5MW you may need to register with us in the future. You have until 30 June 2028 to do this.
I don’t know – contact us at
Does it have a capacity between 20MW and 50MW?
Yes – you should already have a PPC permit. If notcontact the NIEA.
No – go to step 4.
I don’t know – contact us at
Does it fit one of the exclusions listed in the Directive (see text below)?
Yes – this legislation does not apply to you.
No – continue to step 5.
Not sure – contact us at .
Is your existing medium combustion plant on a PPC permitted Part A or Part B installation?
Yes – NIEA will already have sent you an information notice requiring you to provide information about the medium combustion plant at your installation. They will then vary your permit to include conditions relevant to the medium combustion plant at your installation. Details of the variation fee would have been provided with the information notice. If you have not received an Information Notice from NIEA by 31 May 2023 please contact the NIEA.
No – continue to step 6.
You will need to apply to us for a permit to operate your medium combustion plant now.
If you have more than one medium combustion plant on your site:
When we speak about medium combustion plant we mean an individual boiler, generator or engine. If you have more than one plant on your site you need to think of them individually for the purposes of this flowchart/process.
You can apply for all the medium combustion plant for your site on one application form if you operate them all – as long as the total capacity for the site is less than 50MW.
combustion plant used to propel a vehicle, ship or aircraft;
turbines and engines used on offshore platforms;
some driers;
thermal oxidisers.
There are a number of exemptions listed in Article 6 of the MCP Directive. Plants subject to these exemptions will still need to be permitted but are exempt (sometimes on a time-limited basis) from compliance with ELVs. These include:
plant operating under a certain number of hours (NB on islands):
use of biomass,
plant serving a public District Heating Network.
All exclusions and exemptions have been adopted in the NI regulations. Please use the links to the detail in the Directive to ensure you have checked the full list. If you are still unsure, please contact us at
We use cookies on your computer or mobile device to make this website better.
By clicking Accept or continuing, you agree to our cookie policy. You can change your cookie settings at any time. I Accept CookiesReject AllRead More About Our Cookie Policy
Privacy & Cookies Policy
Privacy Overview
This website uses cookies to improve your experience while you navigate through the website. Out of these cookies, the cookies that are categorized as necessary are stored on your browser as they are essential for the working of basic functionalities of the website. We also use third-party cookies that help us analyze and understand how you use this website. These cookies will be stored in your browser only with your consent. You also have the option to opt-out of these cookies. But opting out of some of these cookies may have an effect on your browsing experience.
Necessary cookies are absolutely essential for the website to function properly. This category only includes cookies that ensures basic functionalities and security features of the website. These cookies do not store any personal information.
Any cookies that may not be particularly necessary for the website to function and is used specifically to collect user personal data via analytics, ads, other embedded contents are termed as non-necessary cookies. It is mandatory to procure user consent prior to running these cookies on your website.